Northern Railway achieves breakthrough on Katra-Banihal section in J&K

The Northern Railway officials said on Wednesday that they have achieved a line and level breakthrough of the longest 12.758 km tunnel between Sumber and Arpinchala station on the Katra-Banihal section under the Udhampur-Srinagar-Baramulla Rail Link (USBRL) project.

Business news  Economy  Investment

The Northern Railway officials said on Wednesday that they have achieved a line and level breakthrough of the longest 12.758 km tunnel between Sumber and Arpinchala station on the Katra-Banihal section under the Udhampur-Srinagar-Baramulla Rail Link (USBRL) project.

Officials said the breakthrough was achieved on the T-49 tunnel, which is going to be the longest tunnel of the Indian Railways surpassing the 11.2 km-long Pir Panjal tunnel constructed by USBRL on the Banihal-Qazigund section.

"The South portal of tunnel T-49 is located in the picturesque Sumber village at a distance of 45 km from district headquarters Ramban at an altitude of 1,200 metres, while the North portal is located near Arpinchala village in Khari Tehsil at an altitude of 1,600 metres.

"T-49 tunnel has two tubes -- one is the main tunnel and the other is the escape tunnel. It has been constructed using a modern drill and blast technique called the New Austrian Tunnelling Method.

"The cross-section profile of the tunnel is modified to give it a horseshoe shape.

"In order to facilitate construction of the longest tunnel, three adits -- Urnihal Adit, Hingni Adit and Kundan Adit -- have also been constructed. The tunnel has a ruling gradient 1 in 80 and a designed speed of 100 Kmph.

"An adit is a horizontal or near-horizontal passageway to a larger underground excavation for the purposes of ventilation, water removal, or auxiliary entrance.

"As per the international standards the escape tunnel constructed parallel to the main tunnel is connected by cross passages at an interval of 375 metres to facilitate rescue and restoration work.

"The work of construction was entrusted by Northern Railways to M/s IRCON International limited which has assigned works in two packages to Messrs HCC and M/s AFCONS," the official said.

"The HCC is executing the work on the 5.1 km stretch length from the south portal and AFCONS is executing the work on the 7.658 km stretch from the north portal.

"Several challenges were encountered in the course of construction such as shear zone, perched aquifer, and highly jointed rock mass, rock problems of squeezing and high ingress of water".


Source : IANS