Is political pressure delaying Jalandhar’s ₹400-crore Surface Water project?

Officials cite pressure over road digging, monsoon disruptions as 92% complete project misses deadline again
Jalandhar’s ₹400-crore Surface Water project
Jalandhar’s ₹400-crore Surface Water projectAI generated image
Published on

The ₹400-crore Surface Water Project in Jalandhar is still under construction, despite missing its original completion deadline. The project was scheduled to be completed in September, but according to the current project status, around 92% of the work has been completed, and a new target of December has been set.

Who is executing the project?

The project is being executed by the Sewerage Board and it is aimed at developing the infrastructure required for supplying surface water to the city.

Also Read
Who is Manjit Singh Bedi? FBI’s most wanted fraud suspect arrested by Jalandhar police
Jalandhar’s ₹400-crore Surface Water project

What is the project about?

The project involves extensive work on underground pipelines and related infrastructure, and since the work requires roads to be dug up at several locations, it has also led to concerns among residents and criticism over road conditions and traffic disruption.

“Political pressure” stalling the project

Municipal Corporation Commissioner Sandeep Rishi, while discussing the progress of the project, said officials also face political pressure over the digging of roads for such works and said questions are raised about why roads are being dug up and why the work is being carried out in different areas.

MC Commissioner explains the project details

The Commissioner said such road excavation is part of the execution of the project and is required for laying the necessary infrastructure and the work therefore involves disruption on roads while the pipelines and other components are being installed.

Also Read
Jalandhar residents still waiting: Key smart city projects still pending after spending ₹535 crore
Jalandhar’s ₹400-crore Surface Water project

Impact of rainfall on such projects

Rishi also highlighted the impact of rainfall on the Surface Water Project and other ongoing civic works and according to him, rain affects the execution of projects and can result in work being stalled for around four months.

This, in turn, slows down the overall progress of the projects.

Repeated delays

The Surface Water Project was originally expected to be completed a lot sooner, however, the deadline was missed and the project remained under execution and with 92% of the work now completed, the authorities have set December as the new target for completion.

Also Read
Is a ‘turncoat dangal’ already taking shape in Jalandhar West ahead of 2027?
Jalandhar’s ₹400-crore Surface Water project

Project worth ₹400 crore

The project is one of the largest works undertaken under Jalandhar’s Smart City-related development programme, with an estimated cost of ₹400 crore and its progress is being monitored through review meetings, while officials have been directed to expedite the remaining work.

True Scoop
www.truescoopnews.com